The product structure of an assembly P is shown in the figure.

Estimated demand for end product P is as follows:

Week 1 2 3 4 5 6
Demand 1000 1000 1000 1000 1200 1200

Ignore lead times for assembly and sub-assembly. Production capacity (per week) for component R is the bottleneck operation. Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is


Answer : (C) 2200