Question No. 157 CSE | GATE 2016

Consider the following processes, with the arrival time and the length of the CPU burst given in milliseconds. The scheduling algorithm used is preemptive shortest remaining-time first.

Process Arrival Time Burst Time
$P_1$ 0 10
$P_2$ 3 6
$P_3$ 7 1
$P_4$ 8 3
 
The average turn around time of these processes is milliseconds ________.

Answer : 8.2 : 8.3


Solution of Question No 157 of GATE 2016 CSE Paper

Gantt chart

Process Number Arrival time Burst time Completion time TAT
1 0 10 20 20
2 3 6 10 7
3 7 1 8 1
4 8 3 13 5
Average turn around time : 33/4 = 8.25

Average turn around time is 8.25.