GATE Papers >> CSE >> 2007 >> Question No 16

Question No. 16 CSE | GATE 2007

Group 1 contains some CPU scheduling algorithms and Group 2 contains some applications. Match entries in Group 1 to entries in Group 2.

Group 1 Group 2
P. Gang Scheduling                                1. Guaranteed Scheduling
Q. Rate Monotonic Scheduling 2. Real-time Scheduling
R. Fair Share Scheduling 3. Thread Scheduling

Answer : (A) P-3 ; Q-2 ; R-1